Power Generating Unit No 3 of Yuzhnoukrainsk Power Station being connected to Ukraine’s electricity supply system
16:51 / 25.03.2009

YUZHNOUKRAINSK, MARCH, 25th, 2009, CONTEXT-PRICHERNOMORIE – Power Generating Unit No 3 of Yuzhnoukrainsk Power Station being connected to Ukraine’s electricity supply system after regular repair, Context-Prichernomorie correspondent reports.

PR Department of the Power Station informed the agency about it today, 25 March.

There were no failures whiling switching the system.

Power Generating Unit No 3 was switched off 11 January, 2009.

Power Generating Units No 1 and 2 are operating with no problems in regular mode.