Dredging is planned in Ilyichivsk port this year
07:30 / 19.02.2015

ODESSA, FEBRUARY 19th, 2015, CONTEXT-PRICHERNOMORIE — This year Ilyichivsk sea port is planned dredging, as well as efforts to reduce energy consumption, Context-Prichernomorie correspondent reports.

The press service of the Administration of the Ports of Ukraine noted today, 19 February.

According to the information, the plans of the infrastructure development in Ilyichivsk port were discussed during the meeting chaired by the Chief of sea port Gennady Skvortsov.

Thus, according to Deputy Chief Engineer of the Sea port administration on the Development Anatoly Lutsenko, this year it is planned to reconstruct the approach channel to 16 meters, dredging of the first bucket of Sukhoi estuary up to 15 meters, the reconstruction of the front wall of the pier ¹1, as well as carrying out the repair (operational) dredging near the port berths 1-29 with bringing depth to the passport stamps.

Also in preparation for the 2016 works on the reconstruction of berths in the current year will be necessary project documentation for berths ¹¹2, 7, 8, 9, and executed the project for the reconstruction of the berth ¹10.

In addition, this year provided the completion of the reconstruction of electric networks for Terminal 1, launched in 2009. The purpose of this work is reducing energy consumption, improving the safety and reliability of reloading works in electric power.

For stable operation of the central boiler plant in 2015 provided for the installation of two modern energy-efficient hot water boilers.

In addition to these projects, in 2015, it is planned to complete project works and the beginning of reconstruction and re-equipment of checkpoints ¹¹1, 2, 3, 4 of Ilyichivsk sea port for a transmission mode, as well as the development of transport infrastructure in the area of the entrance ¹2.